We Completed the Parramatta City Center Office Partition Wall Project in One Week

We completed the office partition wall project in the Parramatta city center within just one week, and our client can return the property to its owner punctually.

This office property lease runs out in two weeks. In order to return the property back to its owner on-time, this reinstate job need finish within two weeks. We met client at the office site and try to remember some details the before office. The best thing is our client kept some old photos, like of doors and wall, and one hard copy of the floor plan. All these information can help us to better understand its before conditions.

This office partition reinstate job includes following items:

  • The office partition wall stands at a height of 3 meters; therefore, we incorporated a steel nogging to reinforce the 64mm steel stud wall.
  • Install R1.5 Earthwool wall insulation to minimize noise transmission between rooms.
  • An APS St George Suite Door Jamb along with a 35mm MDF office door was installed.
  • Install custom-sized APS St George Suite and St Marys Suite Aluminum Doors (featuring 6.38mm Laminate Glass).
  • Paint walls by Dulux Aquanamel Semi Gloss in a matching color, and the doors by Dulux Aquanamel Semi Gloss paint in a matching color.
  • Install 100mm Aluminum skirting board.
  • General clean and remove related debris.

City project is harder than normal job, for harder parking, and limited work time allowed, etc.

It’s very happy to hear our client end the lease successfully and get back the bond in few weeks.